Project | Agency | Type of Fund | Total Project Cost | Status | |
---|---|---|---|---|---|
![]() |
New Cebu International Container Port | DOTR | LOAN | 9.1 B | PROCUREMENT |
![]() |
Subic-Clark Railway Project | DOTR, BCDA | LOAN | 50 B | PROCUREMENT |
![]() |
Ambal-Simuay River and Rio Grande de Mindanao River Flood Control Projects | DPWH | LOAN | 39.2 B | PROCUREMENT |
![]() |
Palanca-Villegas (2nd Ayala) (initially submitted as Ayala Bridge)(part of the Pasig-Marikina and River Manggahan Floodway Bridges Construction Project) | DPWH | LOAN | 1.5 B | BUDGETING |
![]() |
Beata-F.Y. Manalo Bridge (initially submitted as Pandacan-Sta Ana Bridge)(part of the Pasig-Marikina and River Manggahan Floodway Bridges | DPWH | LOAN | 1.3 B | BUDGETING |
![]() |
Blumentritt-Antipolo Bridge(part of the Pasig-Marikina and River Manggahan Floodway Bridges Construction Project) | DPWH | LOAN | 1.1 B | BUDGETING |
![]() |
Marikina-Vista Real Bridge (initially submitted as Kabayan-Katipunan Bridge)(part of the Pasig-Marikina and River Manggahan Floodway Bridges | DPWH | LOAN | 1.8 B | BUDGETING |
![]() |
J.P. Rizal - Lopez Jaena Bridge (initially submitted as Reposo-Guatemala Bridge)(part of the Pasig-Marikina and River Manggahan Floodway Bridges | DPWH | LOAN | 1.6 B | BUDGETING |
![]() |
J.P. Rizal - St. Mary Bridge (initially submitted as JP Rizal-Yale Bridge)(part of the Pasig-Marikina and River Manggahan Floodway Bridges Construction Project) | DPWH | LOAN | 5.7 B | BUDGETING |
![]() |
Mercury-Evangelista Bridge (initially submitted as G. Gabriel Mercury Ave Bridge)(part of the Pasig-Marikina and River Manggahan Floodway Bridges Construction Project) | DPWH | LOAN | 1.3 B | BUDGETING |
![]() |
East-west Bank Bridge 1(part of the Pasig-Marikina and River Manggahan Floodway Bridges | DPWH | LOAN | 1.5 B | BUDGETING |
![]() |
East-west Bank Bridge 2(part of the Pasig-Marikina and River Manggahan Floodway Bridges | DPWH | LOAN | 3.1 B | BUDGETING |
![]() |
North and South Harbor Bridge (initially submitted as Robinson Bridge)(part of the Pasig-Marikina and River Manggahan Floodway Bridges Construction Project) | DPWH | LOAN | 8 B | BUDGETING |
![]() |
Clark International Airport Expansion Project - A. Engineering, Procurement and ConstructionB. O&M Concession | DOTR, BCDA | BUILD AND TRANSFER | 14.9 B | ONGOING CONSTRUCTION |
![]() |
PNR North 2 (Malolos-Clark International Airport-New Clark City)Phase 1: Malolos-Clark International Airport Phase 2: Clark | DOTR | LOAN | 283.6 B | BUDGETING |
![]() |
PNR South Commuter Line (Tutuban-Calamba) PHASE 1 | DOTR | LOAN | 344.6 B | BUDGETING |
![]() |
Metro Manila Subway Project - Phase 1 | DOTR | LOAN | 356.9 B | DETAILED ENGINEERING DESIGN |
![]() |
Binondo-Intramuros Bridge | DPWH | GRANT | 4.6 B | ONGOING CONSTRUCTION |
![]() |
Estrella-Pantaleon Bridge | DPWH | GRANT | 1.3 B | ONGOING CONSTRUCTION |
![]() |
Panguil Bay Bridge Project | DPWH | LOAN | 7.3 B | PROCUREMENT |
![]() |
Bonifacio Global City to Ortigas Center Road Link Project , Phase I, IIA & IIB | DPWH | N/A | 1.8 B | ONGOING CONSTRUCTION |
![]() |
Chico River Pump Irrigation Project | NIA | KLOAN | 4.3 B | ONGOING CONSTRUCTION |
![]() |
Malitubog-Maridagao Irrigation Project, Phase II | NIA | N/A | 5.4 B | ONGOING CONSTRUCTION |
![]() |
PNR South Long-haul (Manila-Bicol) | DOTR | LOAN | 175.3 B | BUDGETING |
![]() |
MRT-LRT Common Station Project | DOTR | N/A | 2.8 B | PROCUREMENT |
![]() |
Iloilo International Airport Project | DOTR | N/A | 30.4B | BUDGETING |
![]() |
New Bohol Airport - O&M Concession | DOTR | N/A | 2.3B | BUDGETING |
![]() |
Bacolod-Silay International Airport Project | DOTR | N/A | 20B | BUDGETING |
![]() |
Laguindingan International Airport Project | DOTR | N/A | 14.6B | BUDGETING |
![]() |
Davao International Airport Development Project | DOTR | N/A | 40.5B | BUDGETING |
Mindanao Rail Project (Phase 1) - Tagum Davao Digos Segment | DOTR | N/A | 35.2B | BUDGETING | |
![]() |
Cavite Industrial Area Flood Management Project | DPWH | LOAN | 9.8B | PROCUREMENT |
![]() |
New Centennial Water Source- Kaliwa Dam Project | MWSS | LOAN | 12.2B | PROCUREMENT |
Metro Manila BRT - Line 1 (Quezon Avenue) | DOTR | LOAN | 4.7 B | BUDGETING | |
![]() |
Metro Manila BRT - Line 2 (EDSA/Central) | DOTR | LOAN | 37.7 B | FOR REVIEW |
![]() |
Regional Fish Port Project for Greater Capital Region (Upgrading / Rehabilitation of Navotas) | DA, PFDA | N/A | 14 B | DETAILED ENGINEERING DESIGN |
Road Network Development Project in Conflict Affected Areas in Mindanao | DPWH | 12.8 B | BUDGETING | ||
Rehabilitation of all Agus-Pulangi Hydroelectric Plant Units | DOE, NPC, PSALM | N/A | TBD | WITH PENDING CONCERNS | |
Mindanao Railway Project (Phase 2) | DOTR | N/A | 71.6 B | WITH PENDING CONCERNS | |
Mindanao Railway Project (Phase 3) | DOTR | N/A | TBD | FOR NEDA BOARD APPROVAL | |
Circumferential Road 3 (C3) Missing Link Project | DPWH | N/A | 10.4 B | FOR NEDA BOARD APPROVAL | |
North Luzon Expressway East, Phase I and II | DPWH | N/A | 44.6 B | FOR NEDA BOARD APPROVAL | |
Pasacao - Balatan Tourism Coastal Highway | DPWH | N/A | 4.7 B | FOR NEDA BOARD APPROVAL | |
Camarines Sur Expressway Project (San Fernando-Pili Section) | DPWH | N/A | 2.2 B | FOR NEDA BOARD APPROVAL | |
Camarines - Catanduanes Friendship Bridge (Nationwide Island Provinces Link Bridges) | DPWH | N/A | 22 B | FOR NEDA BOARD APPROVAL | |
Panay-Guimaras-Negros (PGN) Island Bridge Project | DPWH | N/A | 27.1 B | FOR NEDA BOARD APPROVAL | |
Bohol - Leyte Link Bridge (included in the Nationwide Island Provinces Link Bridges) | DPWH | N/A | 27.1 B | FOR NEDA BOARD APPROVAL | |
Cebu - Negros Link Bridge (Nationwide Island Provinces Link Bridges) | DPWH | N/A | 14.4B | FOR NEDA BOARD APPROVAL | |
Cebu - Bohol Link Bridge (Nationwide Island Link Bridges) | DPWH | N/A | 56.6 B | FOR NEDA BOARD APPROVAL | |
Davao City Expressway Project | DPWH | N/A | 25.6B | FOR NEDA BOARD APPROVAL | |
Dalton Pass East Alignment Alternative Road Project (East Dalton Bypass Project) | DPWH | N/A | 4.7B | FOR NEDA BOARD APPROVAL | |
![]() |
Quezon-Bicol Expressway | DPWH | N/A | 4 B | FOR NEDA BOARD APPROVAL |
Luzon - Samar Link Bridge (Nationwide Island Provinces Link Bridges) | DPWH | N/A | 57.6 B | FOR NEDA BOARD APPROVAL | |
Leyte - Surigao Link Bridge (Nationwide Island Link Bridges) | DPWH | N/A | 47.3 B | FOR NEDA BOARD APPROVAL | |
Aqueduct No. 7 (AQ-7) | MWSS | N/A | TBD | FOR NEDA BOARD APPROVAL | |
Ipo Dam No. 3 | MWSS | N/A | TBD | FOR NEDA BOARD APPROVAL | |
Ilocos Norte Irrigation Project, Stage 2 | NIA | N/A | 22.6B | FOR NEDA BOARD APPROVAL | |
Bohol Northeast Basin Multipurpose Project | NIA | N/A | 4.1B | FOR NEDA BOARD APPROVAL | |
Asbang Small Reservoir Irrigation Project | NIA | N/A | 1.4B | FOR NEDA BOARD APPROVAL | |
Balo-i Plains Flood Control Project | DPWH | N/A | 2.1B | DETAILED ENGINEERING DESIGN | |
Tumauini River Multipurpose Project | NIA | N/A | 4.4 B | DETAILED ENGINEERING DESIGN | |
Panay River Basin Integrated Development Project | NIA | N.A | 19.3 B | DETAILED ENGINEERING DESIGN | |
Gregorio del Pilar Impounding Project | NIA | N/A | 3.4B | FOR NEDA BOARD APPROVAL | |
Metro Manila BRT - Phase 3 (BGC-NAIA Segment) | DOTR, BCDA | N/A | 46 B | FOR REVIEW | |
Agus 6 Unit 4 Major Rehabilitation Project | DOE, NPC, PSALM | N/A | 504 M | FOR REVIEW | |
Mindoro - Batangas Super Bridge | DPWH | N/A | 30.8 B | FOR NEDA BOARD APPROVAL | |
![]() |
Improvement of remaining sections along Pasig River from Delpan Bridge to Napindan Channel | DPWH | LOAN | 1 B | COMPLETE |
![]() |
Clark Green City Government Center (a component of National Government Administrative Center) The National Government Center will host Satellite Offices of all branches of the Philippine Government; the Executive | BCDA | JV | 1.7B | ONGOING CONSTRUCTION |
![]() |
Clark Green City Commercial Center (a component of National Government Administrative Center) | BCDA | JV | 850 M | ONGOING CONSTRUCTION |
![]() |
Clark Green City Mixed-Income Housing (a component of National Government Administrative Center) | BCDA | JV | 3.3B | ONGOING CONSTRUCTION |
![]() |
Rehabilitation / Improvement of the Zamboanga Fish Port Complex | DA, PFDA | N.A | 1.1B | PROCUREMENT |
![]() |
Nationwide Fish Ports Project (Package III) | DA, PFDA | N/A | 3 B | PROCUREMENT |
![]() |
Pulangi 4 Selective Dredging Phase 3 | NPC | N/A | 244 M | COMPLETE |
Agus 3 Hydroelectric Plant | DOE | N/A | TBD | FOR REVIEW | |
Sheridan-JP Rizal Bridge | DPWH | N/A | TBD | FOR REVIEW |