LIST: Power lines down due to Typhoon Tisoy
Metro Manila (CNN Philippines, December 3) — Although it continues to weaken, Typhoon Tisoy’s wind has disrupted several power lines in the country.
The National Grid Corporation of the Philippines (NGCP) reported Tuesday that the following transmission lines are unavailable:
South Luzon
Daraga-Sorsogon 69kV Line
Customer Affected: SORECO I, SORECO II
Lumban-Caliraya 69kV Line
Customer Affected: BATELEC II
Batangas-Rosario 69kV Line 1
Customer Affected: BATELEC II
Batangas-Limaland 69kV Line
Customer Affected: BATELEC II
Calaca-Balayan-Nasugbu-Calatagan 69kV Line
Customer Affected: BATELEC I
Naga-Libmanan 69kV Line
Customer Affected: CASURECO I
Batangas-Bauan 69kV Line
Customer Affected: First Bay Power Corp.
Batangas-Taysan 69kV Line
Customer Affected: MERALCO, FBPC
Batangas-Mabini 69kV Line 1
Customer Affected: BATELEC II
Lumban-Famy 69kV Line
Customer Affected: FLECO, QUEZELCO II
Gumaca-Atimonan 69kV Line
Customer Affected: QUEZELCO I
Pitogo-Mulanay 69kV Line
Customer Affected: QUEZELCO I
Gumaca-Lopez 69kV Line
Customer Affected: QUEZELCO I
Naga-Iriga 69kV Line
Customer Affected: CASURECO III
Naga-Concepcion 69kV Line
Customer Affected: CASURECO II
Daraga-Sto. Domingo 69kV Line
Customer Affected: APEC
Naga-Tinambac 69kV Line
Customer Affected: CASURECO II
Daraga-Legazpi 69kV Line
Customer Affected: APEC
Sorsogon-Bulan 69kV Line
Customer affected: SORECO I, SORECO II
Daraga-Ligao 69kV Line
Customer affected: APEC
Visayas
Calbayog-Bliss 69kV Line
Customer Affected: SAMELCO I
Palanas-Cara-Catarman-Allen-Lao-ang 69kV Line
Customer affected: NORSAMELCO
Calbayog-Palanas-Cara 69kV Line
Customer affected: SAMELCO I
Palanas-Cara-Catarman-Allen-Lao-ang 69kV Line
Customer affected: NORSAMELCO
NGCP said that there are also 14 230kV transmission lines unavailable, affecting transmission services in Camarines Norte, Camarines Sur, Albay, and Sorsogon.
Meanwhile, the following transmission lines have been restored:
Paranas-Taft-Borongan-Quinapondan 69kV Line
Customer affected: ESAMELCO
Ormoc-San Isidro 69kV Line
Customer affected: LEYECO V, BILECO